Gilgel Gibe III Dam

The Gilgel Gibe III Dam is a 250m high roller-compacted concrete dam with an associated hydroelectric power plant on the Omo River in Ethiopia. It is located about 62 km (39 mi) west of Sodo in the Southern Nations, Nationalities, and Peoples' Region. Once fully commissioned, it will be the third largest hydroelectric plant in Africa with a power output of about 1,870 Megawatt (MW), thus more than doubling total installed capacity in Ethiopia from its 2007 level of 814 MW. The Gibe III dam is part of the Gibe cascade, a series of dams including the existing Gibe I dam (184 MW) and Gibe II power station (420 MW) as well as the planned Gibe IV (1,472 MW) and Gibe V (560 MW) dams. The existing dams are owned and operated by the state-owned Ethiopian Electric Power, which is also the client for the Gibe III Dam.

Gilgel Gibe III Dam
Location of Gilgel Gibe III Dam in Ethiopia
CountryEthiopia
Locationbetween Wolayita Zone and Dawro Zone, Southern Nations, Nationalities, and Peoples' Region
Coordinates6°50′50″N 37°18′5″E
PurposePower
StatusOperational; power station undergoing commissioning
Construction began2006
Opening dateOctober 2015 (October 2015)
Construction costUS$1.8 billion
Owner(s)Ethiopian Electric Power
Dam and spillways
Type of damGravity, roller compacted concrete
ImpoundsOmo River
Height250 m (820 ft)
Length610 m (2,000 ft)
Spillways1
Spillway typefloodgate
Spillway capacity18,000 m3/s (640,000 cu ft/s)
Reservoir
CreatesGilgel Gibe III Reservoir
Total capacity14.7 km3 (11,900,000 acre⋅ft)
Active capacity11.75 km3 (9,530,000 acre⋅ft)
Inactive capacity2.95 km3 (2,390,000 acre⋅ft)
Catchment area34,150 km2 (13,190 sq mi)
Surface area210 km2 (81 sq mi)
Normal elevation893 m (2,930 ft)
Power Station
Commission date2015-2016
TypeConventional
Turbines10 x 187 MW Francis-type
Installed capacity1,870 MW
Annual generation6,500 GWh Est.

The US$1.8 billion project began in 2006 and electricity generation started in October 2015. The remaining generators were operational by 2016. The project has experienced serious delays; in May 2012, full commissioning had been scheduled for June 2013. The dam was inaugurated by Prime Minister Hailemariam Desalegn on 17 December 2016.

Local and international environmental groups forecast major negative environmental and social impacts of the dam and criticized the project's environmental and social impact assessment as insufficient. Because of this and accusations that the entire approval process for the project was suspect, funding for the full construction cost was not secured, as the African Development Bank delayed a decision about a loan pending a review of the dam's environmental impact by its compliance review and mediation unit. This dates back to August 2009 when they accepted a call from NGOs for such a review. In August 2010 Ethiopian Prime Minister Meles Zenawi vowed to complete the dam "at any cost", saying the dam's critics "don’t want to see developed Africa; they want us to remain undeveloped and backward to serve their tourists as a museum."

This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.