Bath County Pumped Storage Station

The Bath County Pumped Storage Station is a pumped storage hydroelectric power plant, which is described as the "largest battery in the world", with a maximum generation capacity of 3,003 MW, an average of 2,772 MW, and a total storage capacity of 24,000 MWh. The station is located in the northern corner of Bath County, Virginia, on the southeast side of the Eastern Continental Divide, which forms this section of the border between Virginia and West Virginia. The station consists of two reservoirs separated by about 1,260 feet (380 m) in elevation. It was the largest pumped-storage power station in the world until 2021, when it was surpassed by the Fengning Pumped Storage Power Station.

Bath County Pumped Storage Station
Location of Bath County Pumped Storage Station in Virginia
CountryUnited States
LocationBath County, Virginia
Coordinates38°13′50″N 79°49′10″W
PurposePower
StatusOperational
Construction beganMarch 1977 (1977-03)
Opening dateDecember 1985 (1985-12)
Construction costUS$1.6 billion
($4.53 billion in 2023 dollars)
Owner(s)Dominion Generation (60%)
LS Power (40%)
Upper dam and spillways
Type of damEmbankment dam
Height (foundation)460 ft (140 m)
Length2,200 ft (670 m)
Dam volume18,000,000 cu yd (14,000,000 m3)
Upper reservoir
Total capacity35,599 acre⋅ft (43,911,000 m3)
Surface area265 acres (107 ha)
Lower dam and spillways
Type of damEmbankment dam
Height (foundation)135 ft (41 m)
Length2,400 ft (730 m)
Dam volume4,000,000 cu yd (3,100,000 m3)
Spillways1
Lower reservoir
Total capacity27,927 acre⋅ft (34,447,000 m3)
Surface area555 acres (225 ha)
Power Station
Coordinates38°12′32″N 79°48′00″W
Commission dateDecember 1985 (1985-12)
TypePumped-storage
Hydraulic head1,262 feet (385 m)
Pump-generators6 × 480/500.5 MW Francis pump-turbines
Installed capacity3003 MW
Overall efficiency79%
Storage capacity11 hours (24,000 MWh)
2017 generation-935 GW·h
Website
Bath County Pumped Storage Station Website

Construction on the power station, with an original capacity of 2,100 megawatts (2,800,000 hp), began in March 1977 and was completed in December 1985 at a cost of $1.6 billion, Voith-Siemens upgraded the six turbines between 2004 and 2009, increasing power generation to 500.5 MW and pumping power to 480 megawatts (640,000 hp) for each turbine. Bath County Station is jointly owned by Dominion Generation (60%) and FirstEnergy (40%), and managed by Dominion. It stores energy for PJM Interconnection, a regional transmission organization in 13 states and the District of Columbia.

This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.